Clearly Croydon Tories are embarrassed by the
problems experienced with the street lighting replacement programme. Labour’s
Cllr Bonner told the Council meeting on 2 December that there had been ‘delays,
technical issues and persistent problems with no street lighting for sometimes
weeks on end. Despite previously
published timetables for the installation on a ward by ward basis there now
seems to be a scattergun approach to the programme’.
Cabinet member Phil Thomas did not provide the information
Cllr Bonner requested of ‘details for every ward that show when street works
commenced/will commence, when they are/were due to be completed, the percentage
that have been successfully connected, the estimated completion date and the
number of complaints received during the installation process’.
Thomas simply said that the ‘core investment
programme continues to progress around the borough by a ward by ward basis. Unfortunately
due to unforeseen engineering difficulties upon UK Power Networks cable network
this has caused a delay in the completion of this work in wards such as New
Addington and Fieldway. These wards are due to be completed by the end of December
1913.’
Complexity
of Programme
The street lighting replacement programme is a complex
one. This is partly due to the fact that existing street lighting runs on two
different systems.
Cllr Thomas told Labour’s Stuart Collins ‘The street lights in the northern two thirds
of the borough so Purley northwards is connected to a dedicated cable network
known as “Croydon Cable Network” this is a switched network which needs to be
abandoned during the replacement programme, to abandon such a network is a
logistical challenge as it needs to be decommissioned section by section which
involve a number of streets at a time.’
Why
Old Columns Remain as Stumps
‘(T)here are a number of stump columns remaining in-situ
as these act as feeder pillars for the neighbouring streets which have not been
replaced as yet. Once the limb of the old network is no longer needed this will
see the corresponding feeder pillars
being removed. Skanksa, UKPowerNetworks continue to work on the stump
decommissioning programme and every effort is being made to minimise the time
in which feeder pillars are kept in-situ.’
‘At this present time it is not possible to say on a feeder pillar basis
when exactly they will be removed…’
Work
Programme Stages
The replacement programme involves several stages of work. What follows is an attempt
to explain it based on answers to questions at the Croydon Council meeting on
Monday 2 December, the experience in Oakhill Rd in Norbury, and explanations
supplied by Skanksa to affected Oakhill residents.
Stage 1. A leaflet informs residents of the
approximate time period when the street light replacement works will commence.
Stage 2. The approximate location of the new
columns are marked in with a cross yellow circle.
Stage 3. Residents concerned about the placing of
columns against their boundary walls/fences should contact the Council and
Skanska to discuss the matter and negotiate the columns to be nearer the kerb.
This was the outcome in respect of 2 lamps in Oakhill Rd and the moving of a
third nearer the entrance to the local community hall.
Stage 4. Holes and dug and the new columns put in.
Stage 5. A hole is dug by each column in order to
given UK Power access to its electricity cable so it can instal a junction box
to connect the new columns to its electricity cable. The new column lights
start operating. The old street light will continue to work.
Stage 6. The hole is then backfilled and
concreted. This ‘Usually takes up to three days after the LC are removed/Jointed for the
reinstatement to commence. The reinstatement will be done over three phases,
Backfill, Concrete & Mastic. The last two may take longer than usual due to
current weather conditions.’ (Marc Zahra, the Public Liaison Officer for
Skanska, email 27 November.)
Stage 7. The concrete is then tarmaced (mastic).
Stage 8. ‘The new street lights then start to
operate alongside the old ones. ‘Once
the associated new lights have been energised and connected to our CMS system
we can then turn off the old street lighting.’ It takes
‘approximately 100 hours burn time for the lamps to achieve their correct level
of illumination. Decommissioning of the old lamps will not affect the new
lighting.’ (Mark Zahra)
Stage 9. The old street light columns will either
be removed or cut down to a stump – see explanation above.
Stage 10. Any pavement repair needed because of
the removal of columns will be carried out.
Stage 10. The stumps will be removed and final
pavement repairs carried out.
Addiscombe
Street Lighting Failure
On 13 November the street light of several streets
in Addiscombe failed. Cllr Thomas told the Council meeting that a Croydon Cable Network cable fault in Addiscombe
Court Rd caused the problem. The failure was reported the same day to UK Power
Networks, and the fault found and rectified on 19th November. He had ‘tasked
officers to escalate the Councils concern with UK Power Networks to see if the
service can be improved.’
Christmas
Lights
The former Labour Council (to May 2006) stopped
funding festive decorations around the borough as according to Cllr Thomas because
Labour ‘were keen for local businesses to fund them.’
‘However through our street lighting contract we will
provide the mechanism for the businesses to attach the decorations on the
street lighting columns, maintain them while they are up and remove them at no
cost. The councils street lighting team sent out a reminder to all district
centres some weeks back asking if they wanted to arrange for festive decorations
to be installed this year and no response has been received from the businesses
from South Norwood High Street, so no decorations are planned to be installed.’
Similarly no response was received from the businesses in London Rd except for
a request from the Town Centre BID to install decorations in London Rd from West
Croydon Station to Oakfield Road, which have been installed.’
Note
The Minutes of the joint Street Lighting Joint Committee with Lewisham
Council held on 16 October have not yet been posted onto the Council’s website,
therefore it is not yet publicly known what they decided. The progress report
considered at the meeting can be seen at https://secure.croydon.gov.uk/akscroydon/images/att2777.pdf.
Unfortunately a lot of the information combines figures for both Boroughs
rather than separately.
Previous Postings on this issue:
http://historyandsocialaction.blogspot.co.uk/2013/10/croydon-issues-update.html
http://historyandsocialaction.blogspot.co.uk/2013/07/room-for-negotiation-on-croydon-street.html
http://historyandsocialaction.blogspot.co.uk/2013/07/hugging-street-lights-in-croydonsw.html
Previous Postings on this issue:
http://historyandsocialaction.blogspot.co.uk/2013/10/croydon-issues-update.html
http://historyandsocialaction.blogspot.co.uk/2013/07/room-for-negotiation-on-croydon-street.html
http://historyandsocialaction.blogspot.co.uk/2013/07/hugging-street-lights-in-croydonsw.html
To contact author: sean.creighton1947@btinternet.com
No comments:
Post a Comment